| 03/09/21 |
4,000.00 |
PRITCHARD WILMOTT PARTNERSHIP |
Place |
Payment to Contractors - Capital |
| 13/08/21 |
4,000.00 |
PRITCHARD WILMOTT PARTNERSHIP |
Place |
Payment to Contractors - Capital |
| 21/02/25 |
3,870.00 |
TURNER WORKS |
Place |
External Design and Supervision Fees |
| 21/03/25 |
3,870.00 |
TURNER WORKS |
Place |
External Design and Supervision Fees |
| 26/11/21 |
3,850.00 |
ARID DESIGN LTD |
Place |
External Design and Supervision Fees |
| 30/07/21 |
3,850.00 |
ARID DESIGN LTD |
Place |
External Design and Supervision Fees |
| 25/04/25 |
3,720.00 |
JOHN O CONNER GROUNDS MAINTENANCE LTD |
Place |
Payment to Contractors - Capital |
| 28/09/22 |
3,667.94 |
ISLAND ROADS SERVICES LTD |
Place |
Payment to Contractors - Capital |
| 03/11/23 |
3,663.94 |
ISLAND ROADS SERVICES LTD |
Place |
Payment to Contractors - Capital |
| 14/04/21 |
3,640.00 |
SHORELINE SURVEYS LIMITED |
Place |
Payment to Contractors - Capital |
| 11/02/26 |
3,581.25 |
ERMC LTD |
Community Services |
Payment to Contractors - Capital |
| 13/08/21 |
3,567.63 |
ERMC LTD |
Place |
External Design and Supervision Fees |
| 11/02/22 |
3,536.00 |
BRIGHSTONE LANDSCAPING LTD |
Place |
Payment to Contractors - Capital |
| 14/06/24 |
3,510.00 |
ERMC LTD |
Place |
External Design and Supervision Fees |
| 17/07/24 |
3,510.00 |
ERMC LTD |
Place |
External Design and Supervision Fees |
| 15/05/24 |
3,510.00 |
ERMC LTD |
Place |
External Design and Supervision Fees |
| 04/05/22 |
3,440.55 |
ISLAND ROADS SERVICES LTD |
Place |
External Design and Supervision Fees |
| 18/01/23 |
3,400.00 |
ARID DESIGN LTD |
Place |
External Design and Supervision Fees |
| 02/06/21 |
3,400.00 |
ARID DESIGN LTD |
Place |
External Design and Supervision Fees |
| 27/07/22 |
3,388.50 |
BEVAN BRITTAN |
Place |
Legal Fees - Other Parties |
| 07/01/22 |
3,378.75 |
ERMC LTD |
Place |
External Design and Supervision Fees |
| 24/12/21 |
3,305.80 |
ERMC LTD |
Place |
External Design and Supervision Fees |
| 22/03/23 |
3,303.00 |
BEVAN BRITTAN |
Place |
External Design and Supervision Fees |
| 13/08/21 |
3,269.68 |
ISLAND ROADS SERVICES LTD |
Place |
Payment to Contractors - Capital |
| 29/03/23 |
3,245.50 |
MCM CONSTRUCTION LTD |
Place |
Payment to Contractors - Capital |
| 18/11/22 |
3,225.00 |
ITD CONSULTANTS LIMITED |
Place |
External Design and Supervision Fees |
| 13/10/21 |
3,200.00 |
ADT FIRE AND SECURITY PLC |
Place |
Payment to Contractors - Capital |
| 25/02/26 |
3,187.50 |
COWAN CONSULTANCY LTD |
Community Services |
Payment to Contractors - Capital |
| 30/11/22 |
3,110.00 |
MCM CONSTRUCTION LTD |
Place |
Payment to Contractors - Capital |
| 02/04/25 |
3,090.00 |
TIM SMART CHARTERED SURVEYORS |
Place |
External Design and Supervision Fees |